11/16/2017
Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement – Planning Engineer Est.
Have any question?
(00) 201277767728
[email protected]
Register
Login
MANAGEME GEMEN NT TEMPLATE Home
Blog
Manag nagemen ementt Templa Template te
Cerami Cer amic c Tiles, Tiles, Terra Terrazzo zzo Tiles Tiles and and Mosaic Mosaics s Method Method State Statemen mentt
Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement Posted by HANY ISMAEL, MSC, PMP
Categories
Date
Comments
MANAGEMENT TEMPLATE
FEBRUARY 10, 2014
0 COMMENT
Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement This procedure outlines the system of control and inspections to be adopted for the fixing on site of tiles and mosaics.
Sign-up now! get useful contents into your email.
Your email address..
SUBSCRIBE Offline
▼
11/16/2017
Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement – Planning Engineer Est.
PROJECT: PROJECT NAME
SECTION:
DATE OF ISSUE FINISHING
SUBJECT:
Dec. 2012 BY: QA/QC ENGINEER
Ceramic Tiles, Terrazzo Tiles And Mosaics Method Statement
APPROVED BY: QEHS MANAGER ACTION
1.
SCOPE This procedure outlines the system of control and inspections to be adopted for the fixing on
VERIFY
Project
Method
Manager
Statement
Project
Sample
Engineer
approval
Store-
Instructions
keeper
FINI/05/A
site of tiles and mosaics. 2.
PROCEDURE .1
A method statement shall be prepared and approved. It shall include: i)
Acceptance conditions for laying e.g. maximum moisture content of substrate,
levelness, soundness, cleanliness, environment.
Project
Offline
FINI/05/A
11/16/2017
Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement – Planning Engineer Est.
ii)
Surface preparation and bonding e.g. bonding agent, bed mix proportions,
Manager
adhesives. Project iii)
Specific requirements with regard to setting out, alignment of joints and cutting. Engineer
.2
iv)
Method of protecting finished work.
v)
Source documents for tiles, adhesive
A sample of tiles shall be prepared on the wall in accordance with the specifications laid
down in the contract and approved by the Consultant. .3
Storage of tiles: i)
Tiles shall be delivered to site palletised, on a clean hard surface free from
contamination by mud or surface water. ii)
Ensure that manufacturer’s instructions in respect of storage conditions of
adhesives are strictly followed. .4
The Project Director/Manager or his designate will confirm that materials are in
compliance with contract specification requirements. .5
In the case of internal wall tiling, work will not proceed until all concealed conduits, pipes,
electrical cables and boxes etc. that penetrate the tiling have been fixed securely in position and making good is complete. Obtain written clearance from MEP Co-ordinator that all their works in that area is clear for taking up the tiling work.
PROJECT: PROJECT NAME
Ref No. FINI/05 PAGE 2 OF 3
SECTION:
DATE OF ISSUE FINISHING
SUBJECT:
Dec. 2012 BY: QA/QC Offline ENGINEER
11/16/2017
Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement – Planning Engineer Est.
CERAMIC TILES, TERRAZZO TILES AND MOSAICS
APPROVED BY: QEHS MANAGER ACTION
.6
Site operatives must observe the following while fixing tiles in addition to the
VERIFY
Gen.
FINI/05/A
Foreman
FINI/05/A
specifications laid down in the contract document. i)
In the case of internal wall tiles, the setting out course or layout course is
established.
Gen.
ii)
Foreman
The level and events of the wall surface should not exceed the allowable
tolerance as specified in the contract. Any such defect should be rectified before proceeding further. iii)
While setting out for floor tiling, establish a datum level for the finished floor and
control the overall level of the finished floor by means of series of spot levels. The Site Engineer will involve Consultant’s representative while fixing levels. iv)
Avoid cutting tiles as far as possible. If cutting cannot be avoided locate cut tiles
where they will be least noticeable, if in doubt refer to specification. v)
The sequence of fixing tiles shall be as follows unless specified otherwise in the
contract: Floor tiles – from the centre of room Internal walls – Upward from the setting out course up to the specified height (in case of false ceiling) otherwise from top and downwards up to starting level. External walls – always from top to bottom covering one horizontal strip after another but preferably to be done in bays. vi)
The mortar or adhesive is spread on the surface using a trowel or blade in thin layers as
specified. vii)
Before placing the next tile take care to allow correct joint width by placing the
correct spacers in all corner joints.
Offline
11/16/2017
Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement – Planning Engineer Est.
viii)
Do not start joint grouting work till tiles are properly fixed to the surface. Normally
the time period varies between 24 hrs to 48 hrs. .7
Protection and Cleaning: i)
Protect external tiling and mosaics from rain and sun until the bed and joints have
set. Continue the protection for the period specified.
PROJECT: PROJECT NAME
Ref No. FINI/05 PAGE 3 OF 3
SECTION:
DATE OF ISSUE FINISHING
SUBJECT:
Dec. 2012 BY: QA/QC ENGINEER
CERAMIC TILES, TERRAZZO TILES AND MOSAICS
APPROVED BY: QEHS MANAGER ACTION
ii)
Do not allow tiling and mosaics to be wetted in shower bath areas for the period
as specified, until the bedding and joints have set and hardened. iii)
Do not permit any traffic at all on the flooring till the tiles are set afterwards permit
light foot traffic only. iv)
For general protection spread white no-staining saw dust over the floor but not
earlier than the period during which grout is hardened.
Offline
VERIFY
11/16/2017
Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement – Planning Engineer Est.
PROJECT: PROJECT NAME
SITE NO.:
Sheet No.
CERAMIC TILES, TERRAZZO TILES AND MOSAICS
SUBCONTRACTOR: CLIENT SECTION OF WORK ____________________________LOCATION _________________
STAGE ITEM Checked by
Offline
11/16/2017
Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement – Planning Engineer Est.
DATE
PREPARATION
1. Method statement approved.
PE 2. Materials to specification (including suitability of adhesive).
SE 3. Check storage condition of materials.SK 4. Establish line and level.SU 5. Check moisture content of substrate.GF 6. Liaise with MEP section for completion of their works.
PE/MEP
7. Acceptance of substrate
GF
Offline
11/16/2017
Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement – Planning Engineer Est.
8. Sample area acceptable.
PE
APPROVAL TO PROCEED WITH LAYING
QA/QC
INSTALLATION
9. Check setting-out
SU
10. Check line and level.
Offline
11/16/2017
Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement – Planning Engineer Est.
SU
11. Check mixing, colour and application of grout.
GF
12. Check sequence of fixing tiles.
SE
APPROVAL TO PROCEED
QA/QC POST 13. Check initial cleaning of work.GF INSTALLATION14. Check protection applied correctly.GF
APPROVAL TO PROCEED
Offline
11/16/2017
Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement – Planning Engineer Est.
CM
CM – Construction Manager, QA/QC – Quality Assurance/Quality Control, PE – Project Engineer, SE – Site Engineer, SU – Surveyor, GF – General Foreman, SK – Storekeeper
Download Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement Word template: Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement
Tag: ceramic tiles, method statement, Mosaics, terrazzo tiles Share:
Hany Ismael, Msc, PMP Hany Ismael is the founder and CEO of Planning Engineer Est. in Egypt. He has started his career back in 2003 as a site engineer, technical oce engineer, planning engineer, planning manager, and nally planning department manager where he has been involved in several mega construction projects in Egypt and Saudi Arabia. In 2016, he established his own company in Egypt “Planning Engineer Est.” Hany gained his MSc degree in project management from Liverpool University-UK 2013-2016, PMP certied from PMI-USA 2010, and BSc Civil Engineer Tanta University-Egypt 2003. Hany provided more than 3,500 hours of planning and project management training on his website planningengineer.net, YouTube channel, and oine courses since 2011. Offline
11/16/2017
Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement – Planning Engineer Est.
He enjoys teaching project management in simple and practical way, and he developed several planning tools, techniques and courses.
Previous post
Download Planning Engineers Preparation Course for Free
Next post
Men and Women abbreviations Mr., Mrs., Miss and Ms February 11, 2014
February 10, 2014
YOU MAY ALSO LIKE
The application of Line of Balance (LOB) method in constr…
MEMO- 15 word templates
25 April, 2017
25 October, 2015
LEAVE A REPLY You must be logged in to post a comment.
Offline
11/16/2017
Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement – Planning Engineer Est.
SEARCH
Search …
PLANNING COURSES Free Arabic Course How to create time schedule with P6 Free
Professional Planning Engineer (PPE) – Online Workshop $665.00
C a ms Management, Extens on o T me EOT an Deays Anays s-On ne Wor s op $399.00
On ne Pr mavera Course or Eng neers & Construct on Managers! $149.00
A vance P ann ng W t Pr mavera Course-Down oa a e $150.00
Quantitative Schedule Risk Analysis with Primavera Online Course $119.00
Offline